Bridge over the Dunajec, Tarnow, Poland - With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method.

Bridge over the Dunajec
Tarnow, Poland

Construction of the 210 m long section between the seventh and tenth bridge piers in 48 casting segments using the balanced cantilever method.

Asukoht
Kategooria
Tellingute projektid
Projekti osalejad
Klient: Contractor Dragados S.A. Field Service PERI Poland Sp. z o.o., Krakau and Warsaw Branch Offices, PERI GmbH Weissenhorn

Projekti ülevaade

Rohkem infot projektist
1 /
3
Bridge over the Dunajec, Tarnow, Poland - With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method.
Bridge over the Dunajec, Tarnow, Poland - With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method.
With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method. For the construction of the motorway bridge near Tarnow, the construction crew achieved a 4 to 5-day cycle thanks to the easy to use, mechanical solution. At the same time, the high requirements concerning the very small tolerances for the variable bridge cross-sections could be fulfilled.

Nõuded ja lahendused

Nõuded
Varying single-cell hollow box cross-section of the superstructure – with uniform width – at heights of approx. 2.50 m to 6.10 m Continuous change in the angles between the outside of the web and the cantilevers Very small tolerances for the variable bridge cross-section 2 carriageways with 13 m widths respectively

Lahendused
Customized planning and static calculations of the complete solutions for the superstructure on falsework as well as the cantilevered construction Optimally matched systems and operational sequences Cantilevered construction solution on the basis of the VARIOKIT engineering construction kit Falsework as the shoring solution for the formwork used for the box girder superstructure of the foreland bridges Maximum adaptability through the formwork solution consisting of girder wall formwork for the various bridge cross-sections Variable slab formwork positioning for adapting to the continuous angle changes between the outside of the web and the cantilevers

Lisaväärtus
Rapid project realization due to the well thought-out and easy handling
Compliance with the required tolerances thanks to the practical formwork adjustment for facilitating accurate construction of the webs
Fast construction progress due to 4 to 5-day cycles for the up to 5 m long concreting sections
Safe working areas and access to all areas of operations without any additional time and effort through the compatibility of the PERI UP modular scaffolding
User-friendly moving process to the next concreting section each time thanks to the hydraulic drive cylinder

Näita rohkem
Malinowski, Site Manager: Bridge over the Dunajec, Tarnow, Poland
Malinowski, Site Manager: Bridge over the Dunajec, Tarnow, Poland
Karol Malinowski
Site Manager
The PERI cantilevered construction solution provided us with many advantages: fast realization due to the well thought-out and easy handling as well as compliance with the required tolerances thanks to the practical formwork adjustment which allowed very accurate construction of the webs. In addition, the compatibility with PERI UP facilitated safe access means and working areas without any extra time and effort - indispensable for the execution of such a project.

Seotud tooted

Kas olete huvitatud PERI abist teie järgmisel projektil?

Helista numbrile +372 677 11 00 või kirjuta e-mailile peri@peri.ee

Location

Bridge over the Dunajec, Poland

Bridge over the Dunajec, Tarnow, Poland - With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method.
Bridge over the Dunajec, Tarnow, Poland - With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method.