Projekti ülevaade
Rohkem infot projektist
Nõuded ja lahendused
Nõuded
Maximum watertightness thanks to no construction joints in the area of the bottom plate up to 1.10-m-thick tunnel top slab 4.70-m-wide passageway for site traffic vaulted sections in the external areas 0.60 to 3.15-m-high beams in the centre of the tunnel
Lahendused
Combination consisting of project-specific formwork carriage constructions and rentable PERI system equipment: 2 formwork carriages for the casting segment in advance, two subsequent slab formwork carriages and a VARIO solution for the elliptical reinforced concrete columns along the tunnel centre. Additionally, two formwork carriages for the southern entrance area with two parallel tunnel constructions.
Lisaväärtus
A 10-day cycle thanks to economical combination consisting of special constructions and rentable system equipment.


Magnus Jakobsson
Site Manager E101
The bottom plate, walls and slabs could be constructed in 10-day cycles with the PERI tunnel formwork. PERI has always provided us with the best solution.