Sports arena Lora, Split, Croatia - The PERI solution served as both shoring and an assembly platform on which the enormous steel trusses of the roof construction were set down, assembled and moved into position.

Sports Arena Lora
Split, Croatia

Multi-purpose hall with octagonal layout, 120 m x 80 m, and 12,500 seats

Finished: 2009 for the handball world championship in Croatia

 

 

Asukoht
Kategooria
Avalikud ja kultuurihooned
Projekti osalejad
Klient: Dinarik d.o.o., Donji Prolozac

Projekti ülevaade

Rohkem infot projektist

Nõuded ja lahendused

 Oliver Pezer, Work preparation and logistics, Statement Sportarena Lora
 Oliver Pezer, Work preparation and logistics, Statement Sportarena Lora
Oliver Pezer
Work preparation and logistics
We chose PERI because of the professional formwork planning and support. All technical requirements were met in a cost-effective way with the PERI systems.

Seotud tooted

Kas olete huvitatud PERI abist teie järgmisel projektil?

Helista numbrile +372 677 11 00 või kirjuta e-mailile peri@peri.ee

Location

Sports Arena Lora, Croatia

Sports arena Lora, Split, Croatia - The PERI solution served as both shoring and an assembly platform on which the enormous steel trusses of the roof construction were set down, assembled and moved into position.
Sports arena Lora, Split, Croatia - The PERI solution served as both shoring and an assembly platform on which the enormous steel trusses of the roof construction were set down, assembled and moved into position.